In Progress

Project Details

Project NameTinbridge Phase II Utility Improvements
Completion DateDecember of 2021
Major Work Areas IncludeTinbridge Hill Neighborhood Between Taylor and Federal Streets and 2nd and 5th Streets
Work Includesreplacement and rehabilitation of public utilities; 8” domestic water line and associated appurtenances along sections of Taylor, Monroe, Polk, Jackson, 3rd and 4th Streets; storm sewer structures and associated piping along 4th Street; new sanitary manholes; new sidewalk, handicapped ramps, and segmental retaining walls along 4th and Monroe Streets; utility trench pavement patching throughout and milling and pavement overlay of portions of 4th & Jackson Streets
Project UpdatesThere are no urgent updates at this time.

Project Details

Project NameCity of Lynchburg-Young Place BMP Retrofit
Completion DateOctober 2021
Major Work Areas IncludeFishing Creek Watershed
Work Includesheavy vegetation and tree clearing; stream erosion impact restoration and log-toe protection addition; stream bank bouldering and shielding; new precast concrete endwalls, structures, and piping; topographic modifications; gabion weir damming; articulated concrete block forebay shielding; choir matting and stream bank planting; and enkamatting emergency spillway armoring
Project UpdatesThere are no urgent updates at this time.

Coming Soon

f.l. showalter logo

Project Details

Project NameSunbury Place Culvert Replacement
Completion DateDuring the months of May & June of 2020
Major Work Areas IncludeThe storm culvert beneath Sunbury Place between Buckingham Drive and end of cul-de-sac
Work IncludesConstruction of a new stormwater system culvert to replace existing infrastructure, replacement and improvement of existing domestic water service piping adjacent culvert footprint during course of work, and various street repairs
Project UpdatesThere are no urgent updates at this time.

Project Details

Project NameTwo Creeks Drive Stormwater Outfall Improvement
Completion Dateduring the mid summer of 2020
Major Work Areas IncludeThe northeast corner of Two Creeks Drive and adjoining residential parcels
Work IncludesConstruction of new stormwater system piping and structures to manage outflow during major storm events
Project UpdatesThere are no updates at this time.

Recently Completed

Project Details

Project NameBoonsboro Road Stormwater Improvements
Completion DateTo be resumed and completed during the late winter/early spring of 2020
Major Work Areas IncludeThe commercial corridor of Boonsboro Road between Trents Ferry Road and Clayton Avenue
Work IncludesMajor stormwater management enhancements to prevent “ponding” in Boonsboro Road during major storm events and redirecting stormwater “sheeting” across the main entrance of an adjacent commercial shopping center, localized asphalt pavement trench repairs; various street curbing and entrance replacement and remediation 
Project UpdatesThere are no urgent updates at this time.

Project Details

Project NameMoreview Drive Culvert Replacement
Completion DateDuring the months of January, February, and March of 2020
Major Work Areas IncludeThe storm culvert beneath Moreview Drive between Chesterfield Road and Cupola Street
Work IncludesConstruction of a new stormwater system culvert to replace existing infrastructure, some stream rehabilitation and tree planting, replacement and improvement of existing domestic water service piping adjacent culvert footprint during course of work, and various street repairs
Project UpdatesThere are no urgent updates at this time.

Project Details

Project NameTate Springs Road Storm Sewer Replacement
Completion DateFebruary of 2020
Major Work Areas IncludeThe commercial intersection at Tate Springs Road and Thomson Drive
Work IncludesStormwater system remediation to eliminate previous penetrations from obstructing stormwater outflow during storm surges by bypassing existing infrastructure, asphalt pavement trench repairs throughout, various street curbing replacement and remediation
Project UpdatesThere are no urgent updates at this time.

Project Details

Project NameFairview Heights Water and Sewer Rehabilitation
Completion DateJanuary 2020
Major Work Areas IncludeNeighborhoods southwest of Campbell Avenue including those served by Light, Gills, Carter, Sabine, and Mackell Streets and portions of Nelson Street and Fairview Avenue
Work Includesmajor domestic water and sanitary sewer overhauls, some stormwater management enhancements, new domestic metering and fire service hydrants, asphalt pavement trench repairs throughout with some street-width complete asphalt pavement overlays, various sidewalk and street curbing replacement and remediation
Project UpdatesThere are no urgent updates at this time.